Smith Springs Community Center & Park Master Plan

Construction began in March 2017 on the new community center at 2801 Smith Springs Road. In addition to the design of the center a master plan for the entire 15-acre park is being developed. Construction is expected to take 12 - 14 months.

Construction Schedule

  • May 2017: Building Pad, footings, and underground work
  • June 2017: Slab on grade, CMU walls
  • July 2017: CMU walls, structural steel joists, and deck for one story portion
  • August 2017: CMU walls, joist, and deck for gym, second-floor walls, joists and deck
  • September 2017: Roofing, exterior skin
  • October 2017: Exterior skin, MEP rough-in
  • November 2017: Install glass, Prime/paint inside
  • December 2017: Complete brick and metal panels on exterior, interior finishes (Ceiling, flooring)
  • January 2018: Complete finishes on interior
  • February 2018: Install owner furniture, Final paint, casework installation,
  • March 2018: Punch list on new facility

Final Community Design Presentation

The design for the Smith Springs Community Center was presented to the public in April 2016.

First Public Meeting

On Tuesday, March 10, 2015 the community was invited to discuss the project at a public meeting. Visit the links below to see the design team’s presentation and a summary of the comments and ideas generated by participants.

Second Public Meeting

A second public meeting was held on Thursday, April 16, 2015. Visit the links below to see the design team’s presentation, minutes from the meeting and comments from participants.

You can email Rebecca Ratz, email Tim Netsch, or call 615-862-8400 with questions or comments.