Watch Us Build

Artist's Rendering
of Finished Plant (Central)
Project Timelines
Central Biosolids Project Timeline
- 2004 October
- Issue Requests for Qualifications for Design/Builders
- 2004 October
- Issue Requests for Proposals
- 2004 November
- Receive Statements of Qualification
- 2005 March
- Receive Design/Build Proposals
- 2005 June
- Issue Notice to Proceed to Design/Builder
- 2008 February
- Begin Start-Up of New Biosolids Facilities
- 2009 March
- Final Completion of Biosolids Project
Dry Creek Facility Improvement Project Timeline
- 2003 August
- Begin Design for Biosolids Improvements
- 2004 October
- Complete Design
- 2005 February
- Receive Bids for Construction
- 2005 July
- Begin Construction
- 2006 September
- Start-up of New Odor Control Facilities
- 2008 April
- Start-up of New Biosolids Facilities
- 2008 September
- Final Project Completion
Central Odor Control Project Timeline
- 2004 February
- Begin Design for Odor Control Improvements
- 2004 October
- Complete Design
- 2005 February
- Receive Bids for Construction
- 2005 July
- Begin Construction
- 2006 September
- Start-up of New Odor Control Facilities
Construction Highlights
(Select an image below to preview in separate window)
Central Biosolids Project
- 2004

- July 2004

- December 2005

- January
2006

- February
2006

- March
2006

- May 2006

- June 2006

- July 2006

- July 2006

- July 2007

- July 2007

- September 2007

Central Odor Control Project
- July
2005

- October 2005

- January 2006

- February 2006

- June 2006

- June 2006

- July 2006

- July 2006

- August 2007

Dry Creek Facility Improvement Project
- October
2005

- November
2005

- December
2005

- March 2006

- May 2006

- June 2006

- July 2006

- December 2006

- March 2007

- August 2007