Construction Photo Archive
March 2003

2002 AUG | SEP | OCT | NOV | DEC
2003 JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV | DEC

click image to see larger view

photo
Steel & piping progress
photo
Steel progress

photo
Storm sewer ST-1
outfall to structure
photo
X-brace installation
row D-E
photo
Condenser water
branch header
photo
Decking pins row
G-A line 1-2

photo
Progress viewed N-S
photo
Progress
photo
Steel progress is at
elevation of 36 feet
photo
Condenser water heaters
at elevation of 29 feet
photo
Propane tank
pad excavation

photo
Propane tank placement
photo
Block Row E line
photo
Cable tray Row A-B Line
photo
Chill Water header
leaving bldg.
photo
NDES hi-volt duct
view #1
photo
EDS manhole #1
wall form
photo
Propane Tank
awaiting backfill