| "I Want to... Submit a Project." Facility
Construction and Rehabilitation Project Procedures for Integration
of
1. Funding requested for project(s) through the annual Capital Budget process. (Funding for projects may originate from various sources, including fund balance, bonds or notes, grants, federal funding, and other sources.) 2. When initiating a project:
3. Request for Proposal (RFP) Process for Soliciting Design Professionals: A project Scope of Work" is developed by the requesting department (requesting department may include the Board of Education, Parks, Public Works, and Real Property Services) and forwarded to the ADA Compliance Division for review and recommendations. The requesting department works with the Purchasing Division to finalize the RFP, which is then published/advertised. A pre-proposal conference is scheduled with:
If required, amendments to original documents are completed by the requesting department and the Purchasing Division and forwarded to all offerors. Upon receipt by the Purchasing Division, proposals are evaluated by a committee that may be comprised of the following members:
4. Contract Practice - The standard template for contracts includes:
5. Pre-design Meeting - The pre-design meeting is an informational session to further clarify design requirements for the project. The requesting department, ADA Compliance Division, and the design professional(s) discuss the scope of work. 6. Schematic Design Meeting - The schematic design meeting is a working session to review in-progress design requirements and 95% schematic design plans for the project which includes ADA requirements. The requesting department and the design professional(s) will review the programming needs of the user agency(ies). The design professional or project manager is to furnish notes. 7. Final Construction Document Review - Final construction documents are distributed to requesting departments for review and comment to assure that the project scope of work has been completed addressed. The ADA Compliance Division receives two sets of the same documents for review and recommendations for compliance on the following:
The project design shall meet all current and applicable ADA requirements. Plans shall be revised as necessary to resolve deficiencies. Project addenda or change orders will follow the same review process to assure that recommended changes meet the requirements of the ADA. The design professional or project manager is to furnish meeting notes. 8. Construction Process - The construction process follows the procurement procedures outlined in steps 3 and 4 above. 9. Pre-Construction Meeting - A representative of the requesting department, a member of the ADA Compliance Division staff, and the design professional(s) meet with the selected contractor for a detailed discussion of the project scope of work and required inspections during the course of construction. 10. Construction Inspections
Contractor(s)
shall adhere to all current ADA requirements.
Contact the ADA Compliance Division to obtain this form in an alternate format. Construction Language: All construction activities shall be completed in full compliance Americans with Disabilities Act (“ADA”) and Architectural and Transportation Barriers Compliance Board, Federal Register 36 CFR Parts 1190 and 1191, Accessibility Guidelines for Buildings and Facilities; Architectural Barriers Act (ABA) Accessibility Guidelines; proposed rule, published in the Federal Register on July 23, 2004, as has been adopted by Metro. Contract Language: The contractor shall assure to Metro that all services provided through this contract shall be completed in full compliance with the Americans with Disabilities Act ("ADA") and Architectural and Transportation Barriers Compliance Board, Federal Register 36 CFR Parts 1190 and 1191, Accessibility Guidelines for Buildings and Facilities; Architectural Barriers Act ("ABA") Accessibility Guidelines; proposed rule, published in the Federal Register on July 23, 2004, as has been adopted by Metro. |
Para
recibir este documento en otro formato, por favor contacte a: Tiffy
Barnett, Coordinadora de ADA de Finanzas, 222 3rd Avenue North, Sexto
Piso, Nashville 37201
615-862-5443
General Services > ADA Compliance > Request an Accomodation
|
|
Bidding Opportunities Bulletin |