Metropolitan Government of Nashville and Davidson County, Tennessee
Facility Prioritization List, Updated November 16, 2007.

(Numbers before facility names are numbers assigned in original assessment by Thomas Miller & Associates. They may not be in numerical order in this document. Fields that are blank on the original document are omitted from the text below, to make it read more efficiently.)

Facility 1: Courthouse.
Departments/Tenants: Full occupancy. All Courthouse tenants are current tenants.
Thomas Miller Estimated Cost for ADA Compliance: $2,257,000.
Proposed Construction Date (original): May 03.
Proposed Funding Date: Funded.
Project Status: Complete.
Courthouse former tenants:
Clerk and Master. Accessible interim location, was Metro Center. Accessible final location, Courthouse. Move complete.
Register of Deeds. Accessible interim location, Gaylord Entertainment Center. Accessible final location, Ben West library. Move complete.
Jury Assembly. Accessible interim location, was Metro Center. Accessible final location, Courthouse and Birch. Move complete.
Mayor's Office. Accessible interim location, was Ben West library. Accessible final location, Courthouse. Move complete.
Finance Director's Office. Accessible interim location, was Ben West library. Accessible final location, Courthouse. Move complete.
Council Staff and Offices. Accessible interim location, was Ben West library. Accessible final location, Courthouse. Move complete.
Department of Law. Accessible interim location, was Ben West library and Trial Lawyers building. Accessible final location, Courthouse and Ben West library. Move complete.
Metro Clerk. Accessible interim location, was Ben West library. Accessible final location, Courthouse. Move complete.
Council Chamber. Accessible interim location, was Ben West library. Accessible final location, Courthouse. Move complete.
Criminal Court Clerk. Accessible interim location, was Metro Center. Accessible final location, Birch. Move complete.
Circuit Courts and Judges' Chambers - in Birch Building. Accessible interim location, was Metro Center. Accessible final location, Courthouse. Move complete.
Criminal Courts and Judges' Chambers. Accessible interim location, was Metro Center. Accessible final location, Birch. Move complete.
Chancery Courts and Judges' Chambers. Accessible interim location, Metro Center. Accessible final location, Courthouse. Move complete.
Circuit Court Clerk. Accessible interim location, Metro Center. Accessible final location, Courthouse. Move complete.
Trial Court Administrator. Accessible interim location, Metro Center. Accessible final location, Courthouse. Move complete.
Actual Completion Date: November 06.

2. Ben West Building.
Departments/Tenants: Vacant.
Thomas Miller Estimated Cost for ADA Compliance: $210,649.
Proposed Construction Date (original): July 05.
Proposed Funding Date: Funded.
Project Status: Complete.
Ben West building former tenants:
General Sessions Courts and Judges' Chambers. Accessible interim location, N/A. Accessible final location, Birch.
Criminal Court Clerk. Accessible interim location, N/A. Accessible final location, Birch.
Probation. Accessible interim location, Metro Center. Accessible final location, Ben West Building.
Pre-Trial. Accessible interim location, 222 Building. Accessible final location, Ben West Building.
Actual Completion Date: September 07.

3. Lindsley Hall.
Departments/Tenants: Vacant.
Thomas Miller Estimated Cost for ADA Compliance: $118,878.
Proposed Construction Date (original): January 03.
Proposed Funding Date: Funded.
Project Status: Complete.
Actual Completion Date: 2003.
Lindsley Hall former tenant:
Planning Department. Accessible interim location, N/A. Accessible final location, Metro Office Building.

4. Howard Office Building.
Departments/Tenants: Multi-tenant.
Thomas Miller Estimated Cost for ADA Compliance: $598,014.
Proposed Construction Date (Original): July 04.
Proposed Funding Date: Funded.
Project Status: Design underway. Phase One demolition complete.
Proposed Construction Date (revised): Summer 07.
Howard Office Building former tenants:
Codes Administration. Accessible interim location, N/A. Accessible final location, Metro Office Building.
Election Commission. Accessible interim location, N/A. Accessible final location, Metro Office Building.
Human Relations. Accessible interim location, N/A. Accessible final location, Metro Office Building.
Water Services. Accessible interim location, N/A. Accessible final location, Metro Office Building.
Mapping (Planning Department). Accessible interim location, N/A. Accessible final location, Metro Office Building.
Howard Office Building current tenants:
County Clerk. Accessible interim location, Metro Center. Accessible final location, Howard Office Building.
I T S. Accessible interim location, Metro Center. Accessible final location, Howard Office Building.
Social Services. Accessible interim location, Metro Center winter. Accessible final location, Howard Office Building.

5. Lentz Public Health.
Departments/Tenants: Health.
Thomas Miller Estimated Cost for ADA Compliance: $720,754.
Proposed Construction Date (Original): December 02.
Proposed Funding Date: Funded.
Project Status: Design underway.
Proposed Construction Date (revised): Start spring 08.

7. Criminal Justice Center.
Departments/Tenants: Police, Sheriff, Night Court.
Thomas Miller Estimated Cost for ADA Compliance: $2,150,000.
Proposed Construction Date (original): Not submitted.
Proposed Funding Date: Partially funded.
Project Status: Funding for planning and design approved; capital request for entire Police side renovation pending council approval FY08-09. Funding for full planning council approval FY 07-08.
Proposed Construction Date (revised): TBD.

8. 222 Building.
Departments/Tenants: Multi-Tenant.
Thomas Miller Estimated Cost for ADA Compliance: $1,125,000.
Proposed Construction Date (original): Not submitted.
Proposed Funding Date: FY 08-09.
Project Status: Accessible route and restrooms are available to building occupants and visitors.
Proposed Construction Date (revised): TBD.
222 Building tenants:
General Services. Accessible interim location, N/A. Accessible final location, Metro Southeast and Courthouse. Moved out to final locations.
Finance. Accessible interim location, N/A. Accessible final location, TBD.
Human Resources. Accessible interim location, N/A. Accessible final location, TBD.
Beer Board. Accessible interim location, N/A. Accessible final location, TBD.
Legal Department. Accessible interim location, N/A. Accessible final location, Ben West Library.

9. Centennial Sportsplex.
Departments/Tenants: Parks
Thomas Miller Estimated Cost for ADA Compliance: $850,000.
Proposed Construction Date (original): June 03.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: June 05.

10. Municipal Auditorium.
Departments/Tenants: Municipal Auditorium.
Thomas Miller Estimated Cost for ADA Compliance: $1,400,00.
Proposed Construction Date (original): June 03.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2004.

93. Clifford Allen Building.
Departments/Tenants: Multi-tenant.
Thomas Miller Estimated Cost for ADA Compliance: $82,396.
Project Funding Date: N/A.
Project Status: External path of travel - rehab complete. Plan is to relocate tenants to accessible space.
Clifford Allen Building current tenants:
Property Assessor. Accessible interim location, N/A. Accessible final location, Howard Office Building.
Trustee. Accessible interim location, N/A. Accessible final location, Howard Office Building.
UT Agricultural Extension. Accessible interim location, N/A. Accessible final location, Howard Office Building.
Actual Completion Date: 2002.

E911 Communications Building.
Departments/Tenants: Multi-tenant.
Thomas Miller Estimated Cost for ADA Compliance: $175,970.
Project Status: External path of travel, automatic doors - building currently being evaluated for renovation.

11. Juvenile Justice Center.
Departments/Tenants: Multi-tenant.
Thomas Miller Estimated Cost for ADA Compliance: $258,188.
Proposed Construction Date (original): May 03.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: Oct. 05.
Juvenile Justice Center tenants:
Juvenile Courts and Judges' Chambers. To remain..
Juvenile Court Clerk. To remain.
Public Defender. To remain.
District Attorney. To remain.

98. Market Building.
Departments/Tenants: Farmers' Market.
Thomas Miller Estimated Cost for ADA Compliance: $43,332.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2002 and 2005.

104. Fire Department Headquarters.
Departments/Tenants: Fire Department.
Thomas Miller Estimated Cost for ADA Compliance: $143,548.
Proposed Construction Date (original): Year 5.
Proposed Funding Date: Funded.
Project Status: Substantial completion mid to late Nov 07.
Proposed Construction Date (revised): Fall 06.

107. Ambulance Center.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $86,210.
Proposed Construction Date (original): Year 1.
Proposed Funding Date: N/A.
Project Status: Program has been relocated to compliant facility.
Actual Completion Date: 2006.

29. Fire Academy.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $127,633.
Proposed Construction Date (original): Year 3.
Proposed Funding Date: FY 10-11.

106. Fire Prevention Bureau.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $112,540.
Proposed Funding Date: Funded.
Project Status: Program will relocate to new HQ, projected completion 11-07.
Proposed Construction Date (revised): Fall 06.

121. Engine Company 14, including Com. House
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $265,328.
Proposed Funding Date: Funded.
Project Status: Construction underway.
Proposed Construction Date (revised): Summer 07.

119. Engine Company 15 (was 22).
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $67,244.
Proposed Construction Date (original): Year 1.
Proposed Funding Date: FY 08-09.

137. Engine Company 22 (was 15).
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $69,498.
Proposed Construction Date (original): Year 2.
Proposed Funding Date: FY 08-09.

129. Engine Company 1.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $60,618.
Proposed Construction Date (original): Year 3.
Proposed Funding Date: FY 10-11.
Project Status: Ramp replacement completed 2005.

105. Engine Company 3.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $62,296.
Proposed Construction Date (original): Year 3.
Proposed Funding Date: Funded.
Project Status: Funded for design/renovation.

138. Engine Company 4.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $60,886.
Proposed Construction Date (original): Year 1.
Proposed Funding Date: FY 10-11.

126. Engine Company 6.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $75,390.
Proposed Construction Date (original): Year 3.
Proposed Funding Date: FY 10-11.

127. Engine Company 7.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $65,504
Proposed Construction Date (original): Year 2.
Proposed Funding Date: FY 09-11.

112. Engine Company 8.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $54,656.
Proposed Construction Date (original): Year 3.
Proposed Funding Date: FY 08-09.

108. Engine Company 9 (Engine Company 5).
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $57,906.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: Aug. 04.

140. Engine Company 10 (new).
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $61,598.
Proposed Construction Date (original): Year 3.
Proposed Funding Date: FY 10-11.

109. Engine Company 11.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $57,262.
Proposed Construction Date (original): Year 1.
Proposed Funding Date: FY 08-09.

110. Engine Company 12.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $69,172.
Proposed Construction Date (original): Year 2.
Proposed Funding Date: FY 08-09.

111. Engine Company 13.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $67,146.
Proposed Construction Date (original): Year 2.
Proposed Funding Date: FY 09-10.

113. Engine Company 16.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $48,730.
Proposed Funding Date: Funded.
Project Status: construction underway.
Proposed Construction Date (revised): Summer 07.

114. Engine Company 17.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $66,496.
Proposed Construction Date (original): Year 1.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: May 05.

115. Engine Company 18.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $61,466.
Proposed Construction Date (original): Year 2.
Proposed Funding Date: FY 09-10.

116. Engine Company 19 1-A-AM.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $85,784.
Proposed Construction Date (original): Year 3.
Proposed Funding Date: FY 09-10.

117. Engine Company 20.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $83,706.
Proposed Construction Date (original): Year 1.
Proposed Funding Date: FY 08-09.

118. Engine Company 21.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $69,210.
Proposed Construction Date (original): Year 2.
Proposed Funding Date: Funded.
Project Status: Funded FY 07-08.

120. Engine Company 23.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $68,106.
Proposed Construction Date (original): Year 1.
Proposed Funding Date: FY 08-09.
Project Status: Ramp replacement completed 2005.

123. Engine Company 24.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $63,482.
Proposed Construction Date (original): Year 1.
Proposed Funding Date: FY 08-09.

122. Engine Company 25.

Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $54,664.
Proposed Construction Date (original): Year 1.
Proposed Funding Date: TBD.
Project Status: Capital request deferred.

125. Engine Company 26.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $60,806.
Proposed Construction Date (original): Year 3.
Proposed Funding Date: FY 10-11.

124. Engine Company 27.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $78,926.
Proposed Construction Date (original): Year 1.
Proposed Funding Date: TBD.
Project Status: Capital request deferred.

128. Engine Company 28.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $59,738.
Proposed Construction Date (original): Year 3.
Proposed Funding Date: FY 10-11.

130. Engine Company 29.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $61,628.
Proposed Construction Date (original): Year 3.
Proposed Funding Date: FY 09-10.

131. Engine Company 30.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $48,132.
Proposed Construction Date (original): Year 1.
Proposed Funding Date: Funded.
Project Status: Ramp replacement completed 2005. Funded for full design/renovation.

132. Engine Company 31.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $53,284.
Proposed Construction Date (original): Year 2.
Proposed Funding Date: Funded.
Project Status: Funded for full design/renovation.

133. Engine Company 32.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $48,522.
Proposed Construction Date (original): Year 1.
Proposed Funding Date: FY 07-08.
Project Status: Capital request deferred.

134. Engine Company 33 and 35.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $62,426.
Proposed Construction Date (original): Year 1 and 2.
Proposed Funding Date: FY 07-08.
Project Status: New station 33 funded; capital request for renovation of old 35 deferred.

135. Engine Company 34.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $53,108.
Proposed Construction Date (original): Year 3.
Proposed Funding Date: FY 09-10.

136. Engine Company 36.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $53,574.
Proposed Construction Date (original): Year 2.
Proposed Funding Date: FY 09-10.

139. Engine Company 37.
Departments/Tenants: Fire.
Thomas Miller Estimated Cost for ADA Compliance: $898,382.
Proposed Construction Date (original): Year 1.
Proposed Funding Date: FY 08-09.

84. Clinic Pharmacy (Leased).
Departments/Tenants: Health.
Thomas Miller Estimated Cost for ADA Compliance: $59,890.
Proposed Funding Date: N/A.
Project Status: Building is no longer in Metro inventory.

83. Downtown Service Center.
Departments/Tenants: Health.
Thomas Miller Estimated Cost for ADA Compliance: $207,116.
Proposed Construction Date (original): December 06.
Proposed Funding Date: N/A.
Project Status: Closed.

102. Nutrition Program.
Departments/Tenants: Health.
Thomas Miller Estimated Cost for ADA Compliance: $46,955.
Proposed Funding Date: N/A.
Project Status: Relocated to Lentz Public Health Center.
Actual Completion Date: April 06.

81. Supplemental Food Warehouse.
Departments/Tenants: Health.
Thomas Miller Estimated Cost for ADA Compliance: $71,461.
Proposed Funding Date: N/A.
Project Status: Relocated to compliant facility.
Actual Completion Date: April 06.

85. Tarbox School (Leased Senior Citizens).
Departments/Tenants: Health.
Thomas Miller Estimated Cost for ADA Compliance: $262,039.
Proposed Funding Date: N/A.
Project Status: Building is no longer in Metro inventory.

82. Downtown Clinic.
Departments/Tenants: Health.
Thomas Miller Estimated Cost for ADA Compliance: $97,148.
Proposed funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2004.

12. East Public Health Center.
Departments/Tenants: Health.
Thomas Miller Estimated Cost for ADA Compliance: $224,792.
Proposed Construction Date (original): December 06.
Proposed Funding Date: FY 08-09.

14. Woodbine Public Health.
Departments/Tenants: Health.
Thomas Miller Estimated Cost for ADA Compliance: $124,272.
Proposed Funding Date: FY 09-10.

30. Head Start Parent Training Center.
Departments/Tenants: Metro Action Commission.
Thomas Miller Estimated Cost for ADA Compliance: $73,350.
Proposed Funding Date: Funded.
Project Status: Will move to new compliant facility in summer 08.
Proposed Construction Date (revised): Winter 06-07.

36. Dudley Head Start Center.
Departments/Tenants: Metro Action Commission.
Thomas Miller Estimated Cost for ADA Compliance: $115,160.
Proposed Construction Date (original): 2004.
Proposed Funding Date: Funded.
Project Status: Complete.
Actual Completion Date: July 07.

35. East Head Start Center.
Departments/Tenants: Metro Action Commission.
Thomas Miller Estimated Cost for ADA Compliance: $50,776.
Proposed Funding Date: N/A.
Project Status: Taken out of service.

13. Metro Action Commission Administrative Office (North Head Start).
Departments/Tenants: Metro Action Commission.
Thomas Miller Estimated Cost for ADA Compliance: $483,490.
Proposed Construction Date (original): 2007.
Proposed Funding Date: Funded.
Project Status: Will move to new compliant facility in summer 08, Lindsley Hall.
Proposed Construction Date (revised): Winter 07-08.
Notes, Explanation of Extension: Space vacated by NCT required extensive renovation and extended design time.

34. Richland Head Start Center.
Departments/Tenants: Metro Action Commission.
Thomas Miller Estimated Cost for ADA Compliance: $105,734.
Proposed Construction Date (original): 2005.
Proposed Funding Date: FY 08-09.
Project Status: Playground refurbished 2003.
Proposed Construction Date (revised): Winter 07-08.

33. Ross Head Start Center.
Departments/Tenants: Metro Action Commission.
Thomas Miller Estimated Cost for ADA Compliance: $531,522.
Proposed Construction Date (original): 2006.
Proposed Funding Date: Funded.
Project Status: Ross students to be relocated to a new compliant facility to be built at Douglas Park by summer 08.
Proposed Construction Date (revised): Winter 07-08.

32. Tom Joy Head Start Center.
Departments/Tenants: Metro Action Commission.
Thomas Miller Estimated Cost for ADA Compliance: $233,944.
Proposed Construction Date (original): 2002.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2003.

31. Woodbine Head Start Center.
Departments/Tenants: Metro Action commission.
Thomas Miller Estimated Cost for ADA Compliance: $80,656.
Proposed Funding Date: N/A.
Project Status: Relocated to ADA compliant Berry School.
Actual Completion Date: 2004.

100. Deaderick Street Transit Mall.
Departments/Tenants: Metro Transit Authority.
Thomas Miller Estimated Cost for ADA Compliance: $12,500.
Project Status: Rehab work to meet program access requirements determined by current MTA ADA audit. Not started.

16. Metropolitan Transit Authority.
Departments/Tenants: Metro Transit Authority.
Thomas Miller Estimated Cost for ADA Compliance: $100,033.
Project Status: Rehab work to meet program access requirements determined by current MTA ADA audits. Minor construction not ADA upgrade.

17. Nashville Convention Center.
Departments/Tenants: Nashville Convention Center.
Thomas Miller Estimated Cost for ADA Compliance: $253,051.
Proposed Construction Date (original): December 02.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2003.

101. Nashville Career Advancement Center.
Departments/Tenants: Nashville Career Advancement Center.
Thomas Miller Estimated Cost for ADA Compliance: $135,796.
Proposed Construction Date (original): January 03.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2004.

73. Antioch Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $35,218.
Proposed Funding Date: Funded.
Accessible Final Location: July 05.
Project Status: Complete.

59. Bellevue Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $190,576.
Project Construction Date (original): 2007-2008.
Proposed Funding Date: 2007.
Project Status: Not yet scheduled per Parks and Greenways Master Plan.
Accessible Interim Location: Other centers available for program access.

141. Bellevue Park (5).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $18,100.
Proposed Funding Date: Funded.
Accessible Final Location: July 05.
Project Status: Complete.

142. Bordeaux Gardens Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $5,800.
Proposed Funding Date: Funded.
Proposed Status: Complete.
Accessible Final Location: March 04.

144. Buena Vista Park (2).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $1,920.
Proposed Funding Date: Funded.
Project Status: Complete.

145. Cane Ridge Park (6).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $99,660.
Proposed Construction Date (original): 2007-2008.
Proposed Funding Date: 2007.
Project Status: Not yet scheduled per Parks and Greenways Master Plan.
Accessible Interim Location: Other ballfields accessible.

152. Cecil Rhea Crawford Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $23,730.
Proposed Construction Date (original): 2008.
Proposed Funding Date: 2008.
Project Status: Not yet scheduled per Parks and Greenways Master Plan.
Accessible Interim Location: Permit holder operates program.

146. Cedar Hill Park (9).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: 66,580.
Proposed Construction Date (original): 2006.
Proposed Funding Date: Funded.
Project Status: Partially complete. Playgrounds complete. Walking trails done.

147. Centennial Park (11).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $418,070.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: March 06.

148. Charlotte Park (2).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $31,000.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: November 03.

71. Cleveland Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $106,332.
Proposed Funding Date: Funded.
Project Status: Will be completed late 2007 (MDHA).
Accessible Interim Location: Programs to be relocated to new McFerrin Center in January 2007.

150. Cleveland Park (2).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $25,920.
Proposed Construction Date (original): 2006-2007.
Project Status: Playground complete. Access to poolhouse late 07 (MDHA).
Accessible Interim Location: Not applicable - off-season construction.

173. Clinton B. Fisk Park (2).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $24,680.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: July 05.

58. Coleman Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $135,046.
Proposed Construction Date (original): 2006-2007.
Proposed Funding Date: Funded.
Project Status: New building [to be] completed February 2008.
Accessible Interim Location: Programs to be relocated to Antioch during construction.

151. Coleman Park.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $9,700.
Proposed Construction Date (original): 2006-2007.
Proposed Funding Date: Funded.
Project Status: Associated with building replacement.

195. Concessions.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $32,800.
Proposed Construction Date (original): 2008.
Proposed Funding Date: 2007-2008.
Project Status: Not yet scheduled per Parks and Greenways Master Plan.

54. Douglas Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $88,266.
Proposed Construction Date (original): Transferred to Metro Action.
Proposed Funding Date: 2007.
Project Status: No longer a Parks facility.
Accessible Interim Location: Programs will relocate to new East Center.

154. Dudley Park (2).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $0.
Proposed Funding Date: N/A.
Project Status: Complete.
Accessible Final Location: August 05.

72. E. S. Rose Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $147,442.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: March 06.

181. E. S. Rose Park (3).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $176,500.
Proposed Construction Date (original): 2007.
Proposed Funding Date: Funded.
Project Status: To be redeveloped by Belmont University 2008-2010.

61. East Park Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $88,354.
Proposed Construction Date (original): 2006-2007.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Interim Location: Existing building remains during construction.

155. Eastland Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $30,150.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: June 06.

190. Edwin Warner Park (28).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $28,830.
Proposed Construction Date (original): 2006.
Proposed Funding Date: 2006.
Project Status: Sports fields [to be] complete spring 2008.

56. Elizabeth Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $46,248.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: August 05.
Project Status: Complete.

156. Elmington Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $2,000.
Proposed Construction Date (original): 2006.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Interim Location: N/A.

157. Ezell Road Park.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $23,830.
Proposed Funding Date: N/A.
Project Status: To be phased out.

153. Fannie Mae Dees Park (4).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $0.
Project Funding Date: N/A.
Project Status: Complete.
Accessible Final Location: August 04.

158. Glencliff High School (2).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $35,270.
Proposed Funding Date: N/A.
Project Status: No longer programmed by Parks.

159. Granberry Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $4,000.
Project Status: Complete.
Accessible Final Location: August 05.

161. Green Hills Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $94,830.
Proposed Construction Date (original): 2006.
Proposed Funding Date: Funded.
Project Status: Complete except stormwater improvements.
Accessible Interim Location: No programs displaced.

166. H. G. Hill Park (2).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $2,660.
Proposed Construction Date (original): 2006-2007.
Proposed Funding Date: Funded.
Project Status: Under construction (private developer).
Accessible Interim Location: No programs displaced.

162. Hadley Park (5).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $70,340.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: March 06.

55. Hadley Park Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $84,076.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: March 06.

163. Hamilton Creek Park (3).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $52,375.
Proposed Construction Date (original): 2006-2007.
Proposed Funding Date: Funded.
Project Status: Playground, parking, restrooms, walk to fixed piers, mountain bike trail access complete. Marina [to be] complete early 2008.
Accessible Interim Location: No programs displaced.

164. Hartman Park (3).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $28,980.
Proposed Construction Date (original): 2006.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Interim Location: Programs at Looby and Hadley.

165. Hope Gardens Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $0.
Proposed Funding Date: N/A.
Project Status: Complete.
Accessible Final Location: November 02.

167. Joelton Park (4).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $68,280.
Proposed Construction Date (original): 2006-2007.
Proposed Funding Date: Funded.
Project Status: Parking, fields, and playground complete; concession stands in progress.

70. Kirkpatrick Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $52,642.
Proposed Funding Date: Funding.
Project Status: Complete.
Accessible Final Location: July 06.

168. Lock Two Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $11,800.
Proposed Funding Date: Funded.
Project Status: Playground complete.
Accessible Final Location: March 04.

62. Madison Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $88,892.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: October 04.

171. Madison Park.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $4,130.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: October 04.

67. McCabe Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $65,056.
Proposed Construction Date (original): 2007-2008.
Proposed Funding Date: Funded.
Project Status: Replacement center in deesign phase; scheduled completion spring 2009.
Accessible Interim Location: Accessible programs at West Center.

169. McCabe Park (7).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $18,150.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Interim Location: February 05.

66. McFerrin Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $65,898.
Proposed Construction Date (original): 2006.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Interim Location: Existing building remains during construction.

170. McKissack Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $0.
Proposed Funding Date: N/A.
Project Status: Complete.
Accessible Final Location: July 04.

15. Metro Parks Headquarters Conference Room.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $70,170.
Proposed Funding Date: N/A.
Project Status: ?
Accessible Interim Location: Adjacent building accessible.

172. Mill Creek Greenway (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $2,500.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: July 05.

69. Morgan Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $60,596.
Proposed Construction Date (original): 2006-2007.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Interim Location: Accessible programs at Looby Center.

64. Napier Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $80,890.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: January 06.

76. Old MTA Building.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $125,838.
Project Status: Not a Parks facility.

174. Paragon Mills Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $30,500.
Proposed Construction Date (original): 2007-2008.
Proposed Funding Date: 2007.
Project Status: Complete.

175. Parmer Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $15,310.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: May 04.

191. Percy Warner Park.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $145,700.
Proposed Funding Date: Funded.
Project Status: Shelters, playgrounds complete; Steeplechase, Steeplecahse office complete.
Accessible Final Location: March 06.

159. Picnic Gazebo.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $4,000.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: March 04.

176. Pitts Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $22,480.
Proposed Construction Date (original): 2006-2007.
Proposed Funding Date: Funded.
Project Status: New playground complete. Ballfield complete.

77. R. H. Boyd Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $62,416.
Project Status: Not a Parks facility.

143. R. H. Boyd - Preston Taylor Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $1,920.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: April 05.

78. Reservoir Head Start and Reservoir Park.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $92,934.
Project Status: Not a Parks Facility.

177. Reservoir Park (4).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $174,000.
Proposed Construction Date (original): 2007.
Proposed Funding Date: 2006.
Project Status: Not yet scheduled per Parks and Greenways Master Plan.

178. Rhodes Park (7).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $116,800.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: April 05.

65. Richard Hartman Park.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $62,820.
Proposed Construction Date (original): 2006.
Proposed Funding Date: Funded.
Project Status: Complete.

179. Richland Park (2).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $7,200.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: May 06.

180. Riverfront Park (12).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $107,740.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: June 06.

183. Seven Oaks Park (4).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $71,480.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: June 03.

57. Sevier Community Center and Park.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $116,374.
Proposed Construction Date (original): 2007-2008.
Proposed Funding Date: 2007.
Project Status: Scheduled for replacement.
Accessible Interim Location: Accessible programs at E. S. Rose.

184. Shelby Bottoms (2).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $630.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: June 03.

60. Shelby Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $63,476.
Proposed Construction Date (original): 2006.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Interim Location: Accessible programs at Kirkpatrick.

185. Shelby Park (23).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $63,476.
Project Status: Some facilities complete, additional improvements pending master plan to be completed early 2008.

186. Shelby Walk (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $0.
Proposed Funding Date: Funded.
Project Status: Complete.

68. South Inglewood Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $54,636.
Proposed Construction Date (original): 2006-2007.
Proposed Funding Date: Funded.
Project Status: Replacement building to be complete early 2008.
Accessible Interim Location: All programs to relocate in September 2006.

187. South Inglewood Park (2).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $85,050.
Proposed Construction Date (original) 2006-2007.
Project Status: Associated with building replacement.

188. Tom Joy Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $0.
Proposed Funding Date: Funded.
Project Status: Complete.

182. Tony Rose Park.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $0.
Proposed Funding Date: Funded.
Project Status: Complete.

40. Two Rivers Mansion.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $104,200.
Proposed Construction Date (original): 2006.
Project Status: Complete.
Accessible Interim Location: Accessibility through accommodations.

189. Two Rivers Park (19).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $181,620.
Proposed Funding Date: Funded.
Project Status: New clubhouse complete. Wave Country phases 1-3 complete, phase 4 [to be] complete spring 2008.

80. Warner Parks.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $54,566.
Proposed Funding Date: N/A.
Project Status: See Edwin Warner and Percy Warner.

63. Watkins Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $136,146.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: June 05.

192. Watkins Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $3,500.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: June 05.

193. West Park (2).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $31,420.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: August 04.

79. West Park Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $59,370.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: August 04.

194. Whites Creek School Park (2).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $33,540.
Proposed Funding Date: N/A.
Project Status: Fields compliant. Pool no longer a Parks program.

195. Whitfield Park (1).
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $32,800.
Proposed Funding Date: Funded.
Project Status: Complete.
Accessible Final Location: July 04.

41. Z. Alexander Looby Community Center.
Departments/Tenants: Parks.
Thomas Miller Estimated Cost for ADA Compliance: $124,420.
Proposed Funding Date: Funded.
Project Status: Under construction.
Accessible Final Location: July 06.

18. Central Sector Station.
Departments/Tenants: Police.
Thomas Miller Estimated Cost for ADA Compliance: $46,714.
Proposed Funding Date: N/A.
Project Status: Moved to new compliant facility fall 2005.
Actual Completion Date: October 05.

19. East Sector Station.
Departments/Tenants: Police.
Thomas Miller Estimated Cost for ADA Compliance: $44.984.
Proposed Construction Date (original): Fall 06.
Proposed Funding Date: Funded.
Project Status: Complete.
Actual Completion Date: August 07.

27. Police Academy.
Departments/Tenants: Police.
Thomas Miller Estimated Cost for ADA Compliance: $179,106.
Projected Funding Date: FY 10-11.

20. South Precinct.
Departments/Tenants: Police.
Thomas Miller Estimated Cost for ADA Compliance: $35,742.
Proposed Construction Date (original): Spring 07.
Proposed Funding Date: FY 08-09.
Project Status: ADA survey recommendations only. Scope to be assessed.

22. Vehicle Impound.
Departments/Tenants: Police.
Thomas Miller Estimated Cost for ADA Compliance: $25,830.
Proposed Construction Date (original): Spring 07.
Proposed Funding Date: FY 08-09.
Project Status: ADA survey recommendations only. Scope to be assessed.

21. West Sector Station.
Departments/Tenants: Police.
Thomas Miller Estimated Cost for ADA Compliance: $48,322.
Proposed Funding Date: Funded, design only.
Project Status: Land acquisition funds approved. Capital request for design only approved FY 07-08.

New Libraries: Program accessibility of library services has been achieved through rehabilitation of neighborhood libraries, and greatly enhanced by construction of five new libraries. Four new libraries completed in 2000 provided 100% accessible facilities in the four quadrants of the city. The completion of the new main library downtown in 2001 provides an accessible building in the central city.

43. Bellevue Library.
Departments/Tenants: Public Library.
Thomas Miller Estimated Cost for ADA Compliance: $27,960.
Proposed Funding Date: FY 08-09.
Project Status: Planning and design and land acquisition funding in place. Construction funds to be proposed in FY 08-09.

53. Carnegie North Library.
Departments/Tenants: Public Library.
Thomas Miller Estimated Cost for ADA Compliance: $102,570.
Proposed Funding Date: Funded.
Project Status: ADA compliance design/construction underway.

44. Donelson Library.
Departments/Tenants: Public Library.
Thomas Miller Estimated Cost for ADA Compliance: $30,960.
Proposed Funding Date: Funded.
Project Status: ADA compliance design/construction underway.

51. East Library.
Departments/Tenants: Public Library.
Thomas Miller Estimated Cost for ADA Compliance: $70,426.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2001.

52. Edgehill Library.
Departments/Tenants: Public Library.
Thomas Miller Estimated Cost for ADA Compliance: $45,470.
Proposed Funding Date: Funded.
Project Status: ADA compliance design/construction began summer 06.

49. Goodlettsville Library.
Departments/Tenants: Public Library.
Thomas Miller Estimated Cost for ADA Compliance: $75,200.
Proposed Funding Date: FY 06-07 and FY 07-08.
Project Status: Planning and design and land acquisition funding in place; capital request for construction funds approved FY 07-08.

94. Green Hills Library.
Departments/Tenants: Public Library.
Thomas Miller Estimated Cost for ADA Compliance: $41,461.
Proposed Construction Date (original): N/A.
Proposed Funding Date: N/A.
Project Status: Replaced.
Actual Completion Date: 2000.

50. Hadley Park Library.
Departments/Tenants: Public Library.
Thomas Miller Estimated Cost for ADA Compliance: $76,440.
Proposed Funding Date: Funded.
Project Status: ADA compliance design/construction underway.

48. Inglewood Library.
Departments/Tenants: Public Library.
Thomas Miller Estimated Cost for ADA Compliance: $34,900.
Proposed Funding Date: Funded.
Project Status: ADA compliance design/construction underway.

96. Mary and Charles Pruitt Library.
Departments/Tenants: Public Library.
Thomas Miller Estimated Cost for ADA Compliance: $76,747.
Proposed Funding Date: Funded.
Project Status: ADA compliance design/construction underway.

47. Old Hickory Library.
Departments/Tenants: Public Library.
Thomas Miller Estimated Cost for ADA Compliance: $35,470.
Proposed Funding Date: Funded.
Project Status: ADA compliance design/construction underway.

46. Richland Park Library.
Departments/Tenants: Public Library.
Thomas Miller Estimated Cost for ADA Compliance: $41,380.
Proposed Funding Date: Funded.
Project Status: ADA compliance design/construction underway.

42. Southeast Library.
Departments/Tenants: Public Library.
Thomas Miller Estimated Cost for ADA Compliance: $35,360.
Proposed Funding Date: Funded.
Project Status: ADA compliance design/construction underway.

45. Thompson Lane Library.
Departments/Tenants: Public Library.
Thomas Miller Estimated Cost for ADA Compliance: $32,070.
Proposed Funding Date: Funded.
Project Status: ADA compliance design/construction underway.

92. Administration Building/Main Center.
Departments/Tenants: Public Works.
Thomas Miller Estimated Cost for ADA Compliance: $244,405.
Proposed Funding Date: FY 08-09.
Project Status: Program will be relocated to new facility in 2009.

91. East Service Center.
Departments/Tenants: Public Works.
Thomas Miller Estimated Cost for ADA Compliance: $154,547.
Proposed Funding Date: FY 07-08.
Project Status: Two of three buildings completed.
Actual Completion Date: 2003.

87. Engineering Building.
Departments/Tenants: Public Works.
Thomas Miller Estimated Cost for ADA Compliance: $62,580.
Proposed Funding Date: FY 06-07.
Project Status: Program will be relocated to new facility in 2009.

88. Special Operations.
Departments/Tenants: Public Works.
Thomas Miller Estimated Cost for ADA Compliance: $84,068.
Proposed Funding Date: FY 06-07.
Project Status: Program will be relocated to new facility in 2009.

89. Staff Services Building.
Departments/Tenants: Public Works.
Thomas Miller Estimated Cost for ADA Compliance: $72,630.
Proposed Funding Date: FY 06-07.
Project Status: Program will be relocated to new facility in 2009.

90. West Service Center.
Departments/Tenants: Public Works.
Thomas Miller Estimated Cost for ADA Compliance: $65,393.
Proposed Funding Date: FY 07-08.

25. Community Services Building.
Departments/Tenants: Sheriff.
Thomas Miller Estimated Cost for ADA Compliance: $65,978.
Proposed Funding Date: FY 08-09.

26. Day Reporting Center.
Departments/Tenants: Sheriff.
Thomas Miller Estimated Cost for ADA Compliance: $252,910.
Proposed Funding Date: N/A.
Project Status: Demolished.
Actual Completion Date: 2005.

24. Hill Detention Center/Administrative Offices.
Departments/Tenants: Sheriff.
Thomas Miller Estimated Cost for ADA Compliance: $313,686.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: September 2004.

97. Metro Davidson County Detention Facility.
Departments/Tenants: Sheriff.
Thomas Miller Estimated Cost for ADA Compliance: $386,616.
Proposed Funding Date: FY 10-11.

28. Sheriff's Training Academy.
Departments/Tenants: Sheriff.
Thomas Miller Estimated Cost for ADA Compliance: $347,444.
Proposed Funding Date: FY 11-12.
Project Status: Some rehab work completed in 2001-2002.

37. Knowles Home.
Departments/Tenants: Social Services.
Thomas Miller Estimated Cost for ADA Compliance: $665,616.
Proposed Funding: N/A.
Project Status: All rehab completed except in patient rooms.
Actual Completion Date: 2002.

39. Randalls Learning Center.
Departments/Tenants: Social Services.
Thomas Miller Estimated Cost for ADA Compliance: $401,644.
Proposed Funding Date: N/A.
Project Status: Surplused, to be disposed.

38. Richland Village.
Departments/Tenants: Social Services.
Thomas Miller Estimated Cost for ADA Compliance: $916,196.
Proposed Construction Date (original): Winter 06-07.
Proposed Funding Date: N/A.
Project Status: Demolished.

225. Additional Restrooms at Gate.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $1,620.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2001.

197. Agricultural Building.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $4,920.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2001.

213. Annex Building.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $0.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2001.

212. Banquet Hall North of Tunnel
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $4,450.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2001 and 2002.

215. Cafeteria (Restaurant).
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $19,140.
Proposed Funding Date: N/A.
Project Status: Complete.

201. Cattle Barn and Judging Arena.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $0.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2005.

221. Cider Shed, Hoot Owl Junction.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $2,650.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2005.

210. Concessions Stand Building.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $0.
Proposed Funding Date: N/A.
Project Status: Out of service.

206. Creative Arts Building (Women's Building).
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $6,450.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2001 and 2002.

200. Dairy Barn (cattle).
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $0.
Proposed Funding Date: N/A.

196. Exhibitors' Building.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $4,280.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2001.

211. Fair Board/Speedway Office Building.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $290,480.
Proposed Construction Date (original): 2003.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2004.

220. Fair Park Office Building and Restrooms.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $18,100.
Proposed Funding Date: N/A.
Project Status: Rehabbed bathrooms. No programs on upper level.
Actual Completion Date: 2001.

209. Grandstand Facility.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $949,700.
Proposed Funding Date: Funded.
Project Status: Accessible ramp to the Grandstands at the south entrance complete.
Actual Completion Date: Spring 07.

219. Hoot Owl Junction.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $0
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2005.

198. Livestock Building (cattle barn C-Z).
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $660.
Proposed Construction Date (original): 2003.
Proposed Funding Date: N/A.
Project Status: Complete.

224. Log Cabin, Hoot Owl Junction.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $2,650.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2005.

202. Milking Parlor.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $1,450.
Proposed Funding Date: N/A.
Project Status: Copmplete.

203. Mule Barn, Fences, Etc.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $0.
Proposed Funding Date: N/A.
Project Status: Closed non-compliant restrooms 2001.

222. Mule Shed, Hoot Owl Junction.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $2,650.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2005.

199. One Story Metal Swine Barn (S-1).
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $660.
Proposed Construction Date (original): 2003.
Proposed Funding Date: N/A.
Project Status: Accessible pedestrian route. Closed non-compliant restrooms, added restroom, trailer, and ramp, 2003.

205. Rabbit and Poultry Barn.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $0.
Proposed Funding Date: Complete.
Actual Completion Date: 2005.

223. Smokehouse, Hoot Owl Junction.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $2,650.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2005.

218. Sorghum Mill Building.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $5,800.
Proposed Funding Date: N/A.
Project Status: Closed at this time. ADA ramp.
Completion Date: 2005.

214. Sports Arena.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $76,140.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2001.

207. Ticket Booths.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $0.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2005.

216. Vaughan Building.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $4,490.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2001.

204. Wilson Hall.
Departments/Tenants: Tennessee State Fairgrounds.
Thomas Miller Estimated Cost for ADA Compliance: $4,110.
Proposed Funding Date: N/A.
Project Status: Complete.
Actual Completion Date: 2001 and 2002.

Total Thomas Miller Estimated Cost for ADA Compliance: $25,385,995.

New Facilities.
Birch Building. Project Status: Complete.
Metro Office Building. Project Status: Complete.
Edmondson Library. Project Status Complete.
Metro Southeast. Project Status: Complete.
North Police. Project Status: Complete.
Fire Hall #38. Project Status: Complete.
CWC Jails. Project Status: Complete.

Old Ben West Library (City Hall).
Departments/Tenants: Multi-Tenant.
Proposed Funding Date: Funded.
Project Status: Hazardous materials abatement underway.
Mayor's Office. Accessible Final Location: Courthouse.
Council Chambers. Accessible Final Location. Courthouse.
Council Offices. Accessible Final Location. Courthouse.
Metro Clerk. Accessible Final Location. Courthouse.
Library Collection. Accessible Final Location: Main Public Library.
Metro Postal Services. Accessible Final Location: Ben West Library.
Metro 3. Project Status: Space in Courthouse currently under construction. Accessible Final Location: Courthouse.
Portion of Legal Department. Accessible Final Location: Courthouse and Ben West Library.
Portion of Finance Department: Courthouse.

End.