We’re Improving the Water System in Your Area!
PROJECT NAME: 17th Ave. North and 18th Ave. North Phase 2 Water Infrastructure Rehabilitation
PROJECT NUMBER: 03-WG-004L
LOCATION: Download Map
- West End from 16th Ave to 21st, Ave.
- 17th Ave from West End to Meharry Blvd.
- Meharry Blvd from 17th Ave to 18th Ave
- 18th Ave from Meharry Blvd to Jefferson St
PROJECT: Water Main construction in 17th/18th/West End and Meharry Blvd.
TIMELINE: Estimated Completion Early 2012
Update: February 2012: Water line construction is complete. Milling and paving will be completed as weather permits.
West End Water Main Project Update
METRO WATER SERVICES CONTACT: Rick Fussell 615-862-4555
Information for residents and business owners: Notification Letter
| Activity | What to expect |
|---|---|
| Roadway Activity | Lane closures and minor delays expected |
| Working Hours | 9:00 am to 7:00 pm, 5 to 6 days per week |
| Service Interruptions | Minor shutdowns to tie main line to existing lines |
Why are we undertaking this project? Upgrade existing water main
Questions which are not addressed through this web site, please email Sonia Harvat.