construction signPROJECT NAME: Mill Creek Sewer Replacement

PROJECT NUMBER: 07-SG-0182

PROJECT: Upgrade existing Sanitary Sewer Trunk Line

TIMELINE: Estimated Completion: Spring 2012

UPDATE: February – 90% complete

METRO WATER SERVICES CONTACT: Rick Fussell 615-862-4555

STATUS: Main pipe installation expected to be completed by the week after Thanksgiving, weather permitting, with the exception of work under Nolensville Road.

Information for residents and business owners:

Activity What to expect
Roadway Activity Final paving on Pettus Road and Old Hickory Blvd – Nov/Dec.
Roadway Activity Culbertson Road road work near Nolensville Road.- Dec/Jan

Why are we undertaking this project? Project consists of removing the existing sanitary sewer line and installing new line to upgrade the system from approx. Bell Road to Nolensville Road

Questions which are not addressed through this web site, please email Sonia Harvat.