North Nashville Bikeway Progress Update

1/13/2020

The project manager for North Nashville Bikeway installation has provided the following updates on progress:

Work accomplished January 6 through 10, 2020

  • New curb ramp installed on DR DB Todd at Robert Churchwell Museum Magnet Elementary across from Wheless.
  • Continued installing turn arrows and cross-walks on Buchanan and Garfield
  • Continued installing signage on Ed Temple
  • Began installation of delineators on Arthur Ave

Two-Week look ahead

  • Complete delineators on Arthur
  • Begin delineators on Ed Temple
  • Complete signage on Ed Temple and Arthur
  • Complete striping on Ed Temple at Jefferson
  • Continue Striping on Buchanan and Garfield
  • Continue work on ped pole footings on Buchanan