Skip to Content
Public Works

Madison Station Boulevard Project

August 2020 Update

The project is currently in procurement for construction.

The Metro Department of Public Works, the designer’s consultants, and Metro Procurement are currently working to solicit competitive construction proposals.

There are numerous parcels involved in this project; right-of-way acquisition is necessary from certain parcels adjacent to the planned roundabout, but only temporary construction easements and a couple of stormwater easements will be necessary from parcels east of Madison Street. Rights of access have been acquired while the acquisition process moves towards real estate closings.

Project Description

Metro Public Works is constructing a new roadway to extend Neelys Bend past Gallatin Pike. This project will include a new roundabout connection near Fifty Forward and Madison Square and include new streetscaping enhancements, sidewalk, a bicycle track, pedestrian amenities, stormwater improvements, and new street lighting.

Project Limits

Gallatin Pike South at Neelys Bend Road to State Route 45 (Old Hickory Blvd).

District 8: Council Member Nancy VanReece

Status

In Progress

  • A new roadway connection between Hardees and Bojangles on Gallatin Pike, connecting to Old Hickory Boulevard in Madison
  • New sidewalk with a bicycle track
  • Storm drainage improvements including new paving, curb, and gutter
  • Pedestrian amenities
  • Streetscaping and street lights
  • Total project cost estimate is $7 million (100% locally funded)
  • Anticipated right-of-way acquisition: 2019 - 2020
  • Obtain construction contractor and CEI: Upon ROW acquisition, 2020
  • Anticipated construction start date: 2020

Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.

  • Right-of-way Acquisition: Closings Underway
  • Complete Construction Plans Preparation: 6/20
  • Utility Relocations:
    • NES Phase 1 Start: TBD
    • NES Phase 2: Completed 4/20
    • Madison Sewer Utility District Start: TBD
  • Advertisement for Bids: Estimated 8/20
  • Groundbreaking: Estimated 10/20
  • Construction Start Date: Estimated Fall 2020
  • Construction Duration: Anticipated 1.5 years (18 months)
  • Construction Completion Date: TBD

For more information, please contact the Public Works project manager at 615-880-1675.

aerial depiction of Madison Station Boulevard driving toward roundabout from one side

aerial depiction of roundabout from other side

aerial depiction of roundabout from third side