Project Limits
Intersection of Estes Road and Hobbs Road
Council District 34: Council Member Sandy Ewing
Phase: Construction
- This week, crews will complete the paving work, weather permitting. Striping will begin after completion of the paving work.
- Final punch list items and demolition of the old signal box foundation are ongoing.
Project Information
This project will include addition of left turn lanes at all four intersection approaches, new sidewalks with curb and gutter and stormwater improvements.
- Estes Road at Hobbs Road Existing Conditions
- Estes Road at Hobbs Road Proposed Conditions
- Intersection Improvements Design Concept
In addition to the intersection improvements project, there are two other Metro Water projects near the intersection of Estes Road and Hobbs Road.
Estes Road and Hobbs Road Area Project Map
Community Engagement
Wednesday, November 6 at 3:30 p.m. NDOT staff held a meeting to discuss the proposed intersection improvements and detour plan for the project.
Project Timeline
Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.
Project Development Schedule Milestones
- Final Construction Plans: Completed January 2025
- Right-of-Way (ROW) Acquisition: Completed March 2025
- Utility Coordination: August 2025
- Initial Utility Relocations (start): June 2025
Construction Schedule Milestones
- Advertisement for Construction: Complete May 2025
- Contract Award: Walker Building Group
- CEI: Consor
- Contract Fully Executed: Complete May 2025
- Estimated Construction Start: Monday, June 2
- Estimated Construction Completion: August 2025
For more information, please contact the NDOT Project Manager at 615-339-1552.