Project Limits
Intersection of Estes Road and Hobbs Road: View the detour plan
Council District 34: Council Member Sandy Ewing
Phase: Construction
- This week, Walker Building Group installed 560' of 12" water main, 11 taps, and 1 fire hydrant on Hobbs Road. All tie-ins are currently exposed on the North end of Estes Road. Prep for service taps will continue.
- The wall at 4701 Estes Road was demoed. The contractor will stack the blocks of the wall on the property until they are ready to re-install the wall.
- Utility coordination is on-going with Metro Water Services, Piedmont Gas, Nashville Electric Service, AT&T, Comcast, and Google (fiber).
- Construction began on Monday, June 2. The intersection of Estes Road and Hobbs Road is closed until August 12.
- On August 12, the intersection will be reopened and the remainder of the work will be completed with ongoing lane closures.
- The working hours for this project are 7 a.m. to 7 p.m. Monday through Friday.
Project Information
This project will include addition of left turn lanes at all four intersection approaches, new sidewalks with curb and gutter and stormwater improvements.
- Estes Road at Hobbs Road Existing Conditions
- Estes Road at Hobbs Road Proposed Conditions
- Intersection Improvements Design Concept
In addition to the intersection improvements project, there are two other Metro Water projects near the intersection of Estes Road and Hobbs Road.
Estes Road and Hobbs Road Area Project Map
Community Engagement
Wednesday, November 6 at 3:30 p.m. NDOT staff held a meeting to discuss the proposed intersection improvements and detour plan for the project.
Project Timeline
Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.
Project Development Schedule Milestones
- Final Construction Plans: Completed January 2025
- Right-of-Way (ROW) Acquisition: Completed March 2025
- Utility Coordination: Underway
- Initial Utility Relocations (start): Underway
Construction Schedule Milestones
- Advertisement for Construction: Complete May 2025
- Contract Award: Walker Building Group
- CEI: Consor
- Contract Fully Executed: Complete May 2025
- Estimated Construction Start: Monday, June 2
- Estimated Construction Completion: To be determined
For more information, please contact the NDOT Project Manager at 615-416-5563.