Project Limits
South side of Harding Place from Danby Drive to Nolensville Pike (5,800 linear feet)
Council District 26: Courtney Johnston
November 2023 Update
Phase: Right-of-Way
The Nashville Department of Transportation and Multimodal Infrastructure (NDOT) is currently working with the Tennessee Department of Transportation (TDOT) to acquire consulting services to perform right-of-way acquisition.
There are numerous parcels involved in this project; right-of-way acquisition is expected to take approximately 12 months. Once the necessary ROW and easements are acquired the Department of Transportation's certification, they will approve Metro to proceed to the construction phase.
Next month: Addition of Tennessee Department of Transportation (TDOT) right-of-way and easement acquisition services.
- Additional annotated images of the Harding Place Sidewalk Improvement Project and Nolensville Road Intersection Improvements
- Harding Place Sidewalk and Pedestrian Enhancement Project Map
- TDOT Pedestrian Network Enhancement Grant Announcement
Project Description
Nashville Department of Transportation is coordinating with the Department of Transportation to construct an 8-foot sidewalk, 4-foot furnishing zone, and curb/gutter along the south side of Harding Place. The new sidewalk will run from the intersection of Danby Drive to Nolensville Pike. This project will extend the existing sidewalk infrastructure, which will extend from I-65 to I-24 on the south side of Harding Place when completed.
In addition, pedestrian enhancements will include ADA ramps, markings, and signals.
- Length: 5,800 linear feet, with curb and gutter
- Cross-Section: 8-ft sidewalk with 4-ft furnishing zone
- Estimated construction cost: 3.5 million ($2.8 million federal funds, $700,000 million local funds)
- Actual design cost: $704,650 ($536,727 federal funds, $140,931 local funds)
- Estimated ROW/utility relocation cost: $1,200,000 ($960,000 federal funds, $240,000 local funds)
- Estimated CEI cost: TBD
- Actual bid construction cost: TBD
Timeline
Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.
- Environmental studies and preliminary plans: 2017-18
- Design and plan development 2018-2019
- Right-of-way Acquisition: TBD
- Utility Relocations: TBD
- Construction Start Date: TBD
- Construction Duration: TBD
- Construction Completion Date: TBD
Phase Two: Nolensville Pike to I24
Status: Complete
- 7600 linear feet of sidewalk, curb and gutter (South side of Harding Place)
- Storm drainage infrastructure improvements and retaining wall construction
- Pedestrian bridge over Seven Mile Creek
- Pedestrian crosswalks and signals, improved lighting
- Construction cost is estimated $4.6 million; $1.9 million in Tennessee Department of Transportation Enhancement Grant funding; $1.0 Metro Water funding, $1.7 million from Nashville Department of Transportation
- Construction start date: July 1, 2015
- Completion date: April 2, 2017
- Prime Contractor Phase 2: Mountain State (DBA HMA)
Phase One: Timberhill Drive to Danby Drive
Status: Complete
- 3200 linear feet of sidewalk, curb and gutter
- Storm drainage improvements including paving portion of road, curb and gutter
- Pedestrian crosswalks and signals
- Native landscaping
- Construction cost estimate is $1.3 million; .8 million in TDOT Enhancement Grant funding
- Completed Fall 2014
For more information, please contact the project manager at 615-862-8595.