Realignment of Crestmoor Road at Hillsboro Pike to align with Glen Echo Road. Project also includes a new water main within Hillsboro Pike.
Crestmoor Road Signage and Pavement Markings Plan
Project Funding: 100% Local
Project Limits
Intersection of Crestmoor Road and Hillsboro Pike
Council District 25: Council Member Jeff Preptit
Project Status
Phase: Construction
The Crestmoor Road at Hillsboro Pike roadway realignment was complete July 2026. The construction team will be paving Crestmoor Road beginning the week of October 26, 2026. Once the paving is complete the project team will be installing permanent pavement markings and the delineators for the bike lane. There will be some paving to follow on Hillsboro Pike from Graybar Lane to the Green Hills Mall entrance.
Project Timeline
Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.
Construction Schedule Milestones
- Advertisement for Construction: September 2023
- Contract Award: October 2023
- Contract Fully Executed: November 2023
- Construction Start: January 2024
- Estimated Construction Completion: August 2026
For more information, please contact the NDOT Project Manager at 615-339-1552.