Project Limits
McGavock Pike to Old Lebanon Pike (0.43 miles)
Council District 15: Council Member Jeff Gregg
Project Update: June 2026
Phase: Pre-Construction
Final construction plans are being reviewed. This quarter, bid documents will be prepared with a goal to send the project for bid in fall 2026.
Project Description
The project will involve the construction of an 8-foot sidewalk and a 4-foot grass furnishing zone with curb and gutter on the north side of Lebanon Pike. In addition, signal upgrades will be made at the intersections of McGavock Pike and Graylynn Drive that will also include ADA ramps, crosswalk markings, and pedestrian signals.
This project is federally funded, locally managed and is monitored by the TDOT Local Programs Development Office.
Project Funding: 80% Federal and 20% Local
- Length: 4,106 linear feet
- Cross-Section: 8-foot sidewalk with 4-foot furnishing zone
- Estimated Project Cost: $3,800,000
Timeline
Note: Estimated timeline dates are subject-to-change based on most current projected schedules from multiple vendors and departments.
Project Development Schedule Milestones
- Consultant Selection: November 2016
- Preliminary Engineering: January 2019
- Environmental/NEPA: Completed June 2017
- Design (plans development): Completed August 2020
- Right-of-Way (ROW) Acquisition: Complete
- Utility Coordination: Complete
- Final Construction Plans: 2026
Construction Schedule Milestones
- Advertisement for Construction: To be determined
- Contract Award: To be determined
- Contract Fully Executed: To be determined
- Estimated Construction Start: late 2027
- Estimated Construction Duration: To be determined
- Estimated Construction Completion: To be determined
For more information, please contact the NDOT Project Manager at 615-862-8748.
Lebanon Pike – looking east from McGavock Pike intersection (beginning of project)
Lebanon Pike at Old Lebanon Pike (end of project)