Project Limits
Intersection of Mt. View Road and Hamilton Church Road
Council District 8: Council Member Deonte Harrell
September 2026 Update
Phase: Construction
This project will add left turn lanes at all four intersection approaches. The Nashville Department of Transportation and Multimodal Infrastructure (NDOT) will begin construction of this project on Monday, September 14. NDOT coordinated with Thomas A. Edison Elementary School, located nearby, to ensure work occurs outside high‑traffic school times.
Working hours: 8:30 a.m. to 2:30 p.m. (after drop‑off and before dismissal).
Due to the limited working hours, the estimated project duration is approximately 3 months.
Design Concept for Mt. View Road and Hamilton Church Road
Project Funding: 100% Local
Project Timeline
Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.
Construction Schedule Milestones
- Advertisement for Construction: Quarter 1 2024
- Contract Award: Quarter 2 2024
- Contract Fully Executed: Quarter 2 2024
- Estimated Construction Start: Quarter 3 2024
- Estimated Construction Completion: Quarter 2 2025
For more information, please contact the NDOT Project Manager at 615-862-8645.