This project will construct intersection improvements along Nolensville Pike at McNally Drive and Natchez Court that were identified in Envision Nolensville as critical to improving pedestrian access and safety along the growing corridor. Intersection improvements include sidewalks, Americans with Disabilities Act (ADA) upgrades (curb ramps, pedestrian lighting, etc.), curb and gutter, striping, transit stop improvements (relocations, shelters, boarding pad, etc.), pedestrian signals and drainage.
Project Limits
Nolensville Pike from McNally Drive to Natchez Court
Council District 26 and 30: Council Member Courtney Johnston and Council Member Sandra Sepulveda
Project Update: June 2026
Phase: Right-of-Way Acquisition
Right-of-way plans are complete and the right-of-way acquisition process is beginning this quarter. Property owners are expected to receive appraisals summer 2026.
Project Timeline
Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.
Project Development Schedule Milestones
- Consultant Selection: Completed July 2021
- Preliminary Engineering: Completed June 2023
- Environmental/NEPA: Completed May 2024
- Design (Plans development): November 2024
- ROW Acquisition start (duration): mid-2026 (anticipated 9-month duration)
- Utility Coordination: mid-2026
- Final Construction Plans: 2027
Construction Schedule Milestones
- Advertisement for Construction: 2027
- Contract Award: To be determined
- Contract Fully Executed: To be determined
- Estimated Construction Start: 2027
- Estimated Construction Completion: To be added after receipt of construction schedule.
For more information, please contact the NDOT Project Manager at 615-862-8748.