Installation of pedestrian hybrid beacons, new pedestrian crosswalks, pedestrian signals, bulb outs, street lights, Americans with Disabilities Act (ADA) compliant curb ramps, and highly visible and reflective crosswalks to reduce pedestrian crashes.
Funding Source: 80% Federal, 20% Local
Project Limits
- Dickerson Pike and Hart Lane
- Dickerson Pike and Lucille Street
- Rosa L Parks Boulevard and Hume Street
- Rosa L Parks Boulevard and Taylor Street
Council District 2, 5, and 19: Council Member Kyonzté Toombs, Council Member Sean Parker, and Council Member Jacob Kupin.
Project Update: October 2025
Phase: Design
This project is currently finalizing the National Environmental Policy Act (NEPA) process. The department anticipates the design process to begin in early 2026.
Project Timeline
Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.
Project Development Schedule Milestones
- Consultant Selection: April 2025
- Preliminary Engineering: June 2025
- Environmental/NEPA: November 2025
- Design (Plans development): early 2026
- ROW Acquisition start (duration to be determined): 2026
- Utility Coordination: 2026
- Final Construction Plans: 2027
Construction Schedule Milestones
- Advertisement for Construction: To be determined
- Contract Award: To be determined
- Contract Fully Executed: To be determined
- Estimated Construction Start: To be determined
- Estimated Construction Completion: To be determined
For more information, please contact the NDOT Project Manager at 615-862-8748.