Installation of pedestrian hybrid beacons, new pedestrian crosswalks, pedestrian signals, bulb outs, street lights, Americans with Disabilities Act (ADA) compliant curb ramps, and highly visible and reflective crosswalks to reduce pedestrian crashes.
Funding Source: 80% Federal, 20% Local
Project Limits
- Dickerson Pike and Hart Lane
- Dickerson Pike and Lucille Street
- Rosa L Parks Boulevard and Taylor Street
Council District 2, 5, and 19: Council Member Kyonzté Toombs, Council Member Sean Parker, and Council Member Jacob Kupin.
Project Update: October 2026
Phase: Design
The 30% preliminary design plans have been completed and are under review. Once the plans are approved, the projects will advance to the 60% design phase late 2026.
Project Timeline
Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.
Project Development Schedule Milestones
- Consultant Selection: April 2025
- Preliminary Engineering: June 2025
- Environmental/NEPA: May 2026
- Design (Plans development): 2026
- Utility Coordination: 2026
- Final Construction Plans: late 2027/early 2028
Construction Schedule Milestones
- Advertisement for Construction: To be determined
- Contract Award: To be determined
- Contract Fully Executed: To be determined
- Estimated Construction Start: To be determined
- Estimated Construction Completion: To be determined
For more information, please contact the NDOT Project Manager at 615-862-8748.